Week 20 at the Clubhouse Development

November 7, 2018

Work on the Clubhouse continued over the Bank Holiday weekend with ‘The Plasters’ completed the inside of the multi-purpose room in just 2 days. There were seven plasters on site both on Saturday and Bank Holiday Monday. The amount of work that these lads have completed in a short few weeks is astounding, and fair play to one and all. We are now moving into the last phase of the development with the kitchen, hallway and toilets needing to be finished and the multi-purpose hall to be floored. So, lets keep up the great work and we will soon have a facility we can all be proud of.